Luton Town's Power Court stadium project has been delayed by a month and hit by a £15 million cost increase. The club confirmed the setback, which is attributed to the discovery of an uncharted Victorian sewer during construction, but maintains the target of a June 2028 completion for the 2028/29 season.
Chief executive Gary Sweet said "the project's delay to an issue involving an uncharted Victorian sewer" had impacted the schedule. Despite this, piling and substructure work is fully complete and the superstructure is progressing, with the West Stand having reached its second floor.
Cost pressures mount
Construction costs have risen sharply due to global market conditions. A 70% increase in oil prices and a 40% year-on-year hike in steel costs, influenced by geopolitical events, have added approximately £15 million to the project's budget. The club is managing these pressures while work continues on site.
The Luton Town Supporters' Trust noted that "any further delays could add to the overall expense and potentially lead to the project's timetable changing." The new 25,000-seat stadium is projected to accommodate average crowds of 16,000 to 18,000 fans in League One, with an additional 4,000 to 5,000 season ticket seats available. Away supporter capacity is also expected to double.
The news comes as Luton Town's strong on-field form provides a positive backdrop. The team is currently fourth in the <a href="/standings">League One table</a> with 23 points from 13 games, riding a four-game winning streak. Their attacking prowess has seen them score 26 goals this season, with an average of 2.0 goal minutes per game. The club will look to continue this momentum in their <a href="/fixtures">next fixture</a> against Portsmouth. The project remains a critical part of the club's future, aiming to unlock greater matchday revenue and fan experience as the team pushes for promotion.